Wednesday, February 11, 2015

Update

3rd floor - nearly all trim is complete and carpet is going in units. 

Building fire safety singage has been installed along with unit number plaques. 







Wednesday, January 14, 2015

Update

The siding is starting to take shape. 



1st floor drywall will be completed by the end of the week. Below are photos of the light tray in the 1st floor elevator lobby. 








Tuesday, January 6, 2015

Update

3rd floor. Accent walls, electrical devices, and kithen floors are being installed. 










Monday, December 29, 2014

Paint

1/2 of 3rd floor is primed. Will texture Tueaday and paint Wednesday. 




Friday, December 5, 2014

Update


The parking lot is nearly complete and we should be wrapping it up on Monday.






3rd floor - the sound / fire channel is being installed followed by drywall.