Monday, December 29, 2014

Paint

1/2 of 3rd floor is primed. Will texture Tueaday and paint Wednesday. 




Friday, December 5, 2014

Update


The parking lot is nearly complete and we should be wrapping it up on Monday.






3rd floor - the sound / fire channel is being installed followed by drywall. 














Thursday, December 4, 2014

Update


The parking lot is moving along and will be complete Friday. 3rd floor half the mechanicals are inspected and we are insulating. Drywall will be loaded later today and we will start rocking Friday. 









Tuesday, November 25, 2014

Update

The roofing system is complete. The parking lot curbs are poured. We are pre-rocking the building now. Should be ready for insulation next week Tuesday on 3rd floor. 








Thursday, November 13, 2014

Roof

The roof is sheathed and dried in. The shingles are being installed. 




Tuesday, November 11, 2014

Roof

The roof is going on and we have about half the building dried in.  


Thursday, October 30, 2014

Update





Half of the roof trusses are now set. 


The transformer pad is set and ready for Alliant to connect the power. 


The Stormwater is also starting to go in. 

Roof trusses

Today is the first day swinging roof trusses. 


Friday, October 24, 2014

Monday, September 8, 2014

Project update

The first floor exterior walls are going up, the pad had been placed for the crane ready to swing 2nd floor trusses Wednesday. 




Wednesday, August 6, 2014

Project Update

The foundation is nearly complete - preparing for pre-cast later this week.