Update
The parking lot is moving along and will be complete Friday. 3rd floor half the mechanicals are inspected and we are insulating. Drywall will be loaded later today and we will start rocking Friday.
Tuesday, November 25, 2014
Update
The roofing system is complete. The parking lot curbs are poured. We are pre-rocking the building now. Should be ready for insulation next week Tuesday on 3rd floor.
Thursday, November 13, 2014
Tuesday, November 11, 2014
Thursday, October 30, 2014
Update
Half of the roof trusses are now set.
The transformer pad is set and ready for Alliant to connect the power.
Friday, October 24, 2014
Monday, September 8, 2014
Project update
The first floor exterior walls are going up, the pad had been placed for the crane ready to swing 2nd floor trusses Wednesday.